• Project Type: Commercial Façade/Brick Work
  • Client: Guildmore
  • Location: Westminster London
  • Architect: N/A
  • Status: Planning
  • Value: Circa £800K

Brief:

To remove the existing brickwork façade 1200sqm on the 8th and 9th floor. Remove the existing insulation and fire barrier layers back to SFS and rebuild back to the new specification.

Project Details

Westminster Green is a prestigious residential development located in Westminster London.

Fire remediation works required due to not meeting current regulations.

Working to a very tight programme and working with multiple trades on the scaffold, the logistics of the site were challenging with all materials man-handled from the basement carpark.

Main Features

  1. Remove all brickwork
  2. Remove balustrade and feature stone and protect
  3. Remove all insulation and fire barrier back to SFS
  4. Beamclad encapsulation of the steels
  5. Install New VCL
  6. Install Rockwool Flexi 200mm
  7. Install New Siniat Board
  8. Install New Breather Membrane
  9. Install Siderise Fire barriers
  10. Install EDPM
  11. Install additional SFS as required
  12. Install brickwork ancillaries
  13. Install Rockwool RW3 insulation
  14. Install Cavity trays
  15. Install Brickwork
  16. Reinstate Balustrade and stonework

Accreditations

Our chosen charity for 2025

Concept to completion

Copyright 2023 Full Works Projects Limited is registered in England & Wales No. 9643365. VAT No. 164 6479 77
Registered Office: 12-16 Lionel Road, Canvey Island, Essex, SS8 9DE

Privacy Policy

Website Design by Pipe Media