Project Type: Commercial Façade Client: Higgins Construction Location: Acton, London Architect: N/A
Status: Planning
Value: Circa £2.5M
Brief: Full reclad project including new cladding and render.
Project Details
Lowry House is owned by the Catalyst Housing association and as part of ongoing fire remediation works, we were appointed by the main contractor Higgins for replacement external façade – cladding and render with all the infill components.
All flats were occupied, and a careful programme had to be adhered to working with the liaising officer with the flexibility to make last minute changes if required.
Working to a very tight programme and working with multiple trades on the scaffold the logistics of the site was very difficult. All materials were stored off site and had to brought to site daily.
Main Features
- Remove all cladding and render, insulation, cappings
- Stage 5 design for all components
- Investigation works
- Supply and Install fire barrier into cavity
- Supply and install new steel cavity closure for the windows within brick area
- Supply and install fire-rated mastic as per design
- External mastic as per design
- Repairs to internal reveals
- Decoration/Carpentry to internal reveals
- Supply and install new fire-rated vents
- Insulation installation
- Y-Wall board installation
- SideRise Fire barriers installation
- Rockpanel & SPS Envirowall installation
Accreditations
Our chosen charity for 2025



Copyright 2023 Full Works Projects Limited is registered in England & Wales No. 9643365. VAT No. 164 6479 77
Registered Office: 12-16 Lionel Road, Canvey Island, Essex, SS8 9DE
Website Design by Pipe Media